|
| |
20185 E. Country Club Drive,
Aventura,
Florida 33180

STRUCTURAL INSPECTION REPORT ON: September 4, 2001
CONCRETE DAMAGE ASSESSMENT REPORT:
- Unit 1901: Observed 6-7 inches of cracked and spalled concrete
along the slab edge. The area of spalled concrete is approximately 1x8x1/2"
depth. The reinforcing bar was rusted and numerous cracks along the stucco and
concrete were observed. See sketch attached for additional details.
- Unit 1701: Observed a 14 inch x 2.5 inch of concrete spalled area
with rusted and exposed rebar at the upper corner section.
- Unit 1601: Observed several cracks along the concrete and stucco
surface and signs of initial spalling
- Unit 1406: Observed a +/- 30 inch x 1.5 inch corner spalling with
exposed and rusted rebar. Cracks were also observed along both sides of the
spalled area.
- Unit 1405: Observed a six (6) inch spalled area. No visible
reinforcing bars or rust was detected at this time.
- Unit 1401: Observed a 21 inch x 3 inch concrete spalled area and
complete shear failure. The reinforcing bars were rusted about 90 – 98% . The
reinforcing bar exhibited flaking and peeling of the rusted steel which needs
immediate repair.
- Unit PH-1: Two areas of damage were observed. The first spalled
area was found 18 –21 inches with 16 and 18" cracks x1/2" width on both sides
of the spalling area. The reinforcing bar was rusted 70- 80 %. The second area
exhibited several cracks approximately 24 inches in length
- Unit 1006: Observed a large section of concrete slab that has been
disintegrated and spalled measuring approximately 7 to 8 feet in length x3"x3"
void along the slab edge. The rusted rebar was sagging a total length of
approximately 6-7 feet x 3 inches deflection. Additionally, 2 cracks were
observed on both sides propagating approximately 2-3 feet. This balcony and
concrete needs immediate repair . See attached sketch and photos for
additional details.
- Unit 801: Observed an 8 inch x ¼" structural cracks along the
balcony edge adjacent to kitchen.
- Unit 705: Observed cracks measuring 6-8 feet x ¼" in thickness.
- Unit 309: No visible cracks or concrete damage at this time.
- Evaluation and Recommendations:
Reference the attached technical specifications titled: " Concrete slab
repairs and spalling areas" for detailed procedures and technical
information regarding the repair of the above units.
The contractor must submit his work schedule to the owner and engineer for
approval prior to commencing repair work. Additionally, the contractor must
apply for permits and submit a work plan in advance of the work schedule.
All work must be coordinated with the property manager and employ high
standards of conduct to minimize tenant disturbance including but not limited to
noise, dust, dirt and trash.
The work area and all access areas and elevators must be kept clean at all
times, and advance work schedule must be submitted in writing prior to each days
work.
All repair work must be inspected by the engineering staff prior, and during
construction to insure compliance with the approved technical specifications and
repair procedures.
Technical specifications for the repair of the spalled concrete and rusted
steel in balconies.
A site assessment and evaluation of each unit including inspection,
photos, and measurements for each damaged area.
Site on the job Inspection and monitoring of work performed by contractor
to insure compliance with contract specifications for concrete repair.
Inspection of work in progress documented by a daily report of inspection
and project photos.
Certified Inspection report containing materials used and adherence to
project specifications, signed and sealed. ( Upon completion and approval of
work)
Project photos containing damaged areas of the concrete slab
Detailed drawings
Based upon a review of the existing building Architectural and Structural
plans and visual observations of the building structure, we offer the following
opinions:
- Due to the nature of reinforcing bar having a cover of ½ inch or less in
some instances, the water being drained from the balcony surface is seeping
around the slab edge into the concrete mass causing rust and oxidation to the
reinforcing steel bars. The reinforcing bar is expanding in volume causing
cracks and spalling to the concrete and stucco.
- The cracks detected along the balcony slabs may also be due to compressive
structural failure of the concrete slab and the following :
- The compressive strength of the concrete is below the design value as
noted in the contract plans and specifications
- The reinforcement in the slab in the form of welded wire mesh may not be
sufficient to resist tension as a result of dead and live loads
- Clearance to the reinforcing steel bars and water intrusion due to heavy
rain fall and insufficient drainage provisions caused deterioration of the
slab and spalling
- As a result of water seepage and since concrete slabs are porous and may
not be sealed properly, water intrusion inside the concrete have rusted the
rebars , causing expansion of concrete mass, cracking and loss in tension
forces.
- Recommendations and Solutions:
We recommend immediate repairs to the damaged concrete and rusted steel
elements as described herein above in accordance with the attached technical
specifications, South Florida Building Code, local codes and design sketches.
The contractor must employ competent workers to comply with "OSHA"
requirements and maintain safe working conditions to all persons involved. All
areas affected by construction and repairs must be sealed off and protected
from falling debris and tools.
As illustrated above, the referenced buildings exhibited structural damage as
well as water problems due to several factors listed. We recommend that
immediate repairs and inspections be conducted as described in items above
"Recommendations and Solutions".
The structural damage to the concrete balconies and water drainage problems
must be corrected immediately to minimize further damage to the structure. Delay
in desperately needed repairs will result in compounded additional cost which
will be minimized upon proper and correct solutions.
This report is made on the basis of what was visible and
accessible at the time of inspection.
This report does not constitute a guarantee that there are no other
deficiencies than those noted, or that additional problems will not occur in the
future. Further, our Company and its employees assume no liability whatsoever as
a result of this assessment and report.
We hope that you were satisfied with the quality and speed of
service and hope that
you will give us the opportunity to work with you in
correcting the above problems based on fast, innovative and quality engineering
solutions.
If you require additional assistance with the above
referenced project, we would be more than happy to provide you with our
technical knowledge and professional experience.
| DATE OF
INSPECTIONS |
AREA
INSPECTED |
UNIT NUMBER |
FINDINGS |
RECOMMENDATIONS |
| MARCH 15, 2002 |
CONCRETE BALCONY SLAB |
UNITS #:909 |
STEEL MUST BE LOWERED @TOP#5 BARS, ATTACH
TAPCONS AND DOWEL BAR TO REPLACE CUT BARS,EPOXY 4" IN SLAB |
CONTRACTOR MUST REPAIR AS PER ENGINEER'S
RECOMMENDATIONS EXTRA COST |
| MARCH 15, 2002 |
CONCRETE BALCONY SLAB |
UNITS #: 1405 |
18" #5 REBAR W/EPOXY |
GC TO TAKE DIGITAL PHOTOS |
| MARCH 15, 2002 |
CONCRETE BALCONY SLAB |
UNITS #: 705 |
REMOVED RUSTED #5 REBAR=8'-5",TO CUT AND
REMOVE (2) PIECES OF#5 STEEL DUE TO CLEARANCE AND POUR WITH APPROVED
MIX.ATTACH W./TAPCONS |
GC TO TAKE DIGITAL PHOTOS (2 hrs) |
| March 18, 2002 |
CONCRETE BALCONY SLAB |
UNITS #:909, # 1405,#705 |
all rebar to have cover of 1/2", clean all
debris & dust |
Contractor to comply w/specifications (2 hrs) |
| March 22, 2002 @1:00pm |
CONCRETE BALCONY SLAB |
UNITS #:909, # 1406,#705, #1006,#806
|
all rebar to have cover of 1/2", clean all
debris & dust, poured with hydro concrete as per approved specifications |
Contractor to comply w/specifications (2 hrs)
Took several photos |
| March 29, 2002 9:00Am
- 12:00Pm |
Concrete Balcony slab |
Units # :901, 1401, 1601, 1901, 801 |
Inspected balcony concrete areas for rusted
rebar, spalling removal and cleaning of surface for pour |
Contractor was instructed to clean rebars
from all rust, remove additional spalled concrete ..Reference Log Book for
details, took digital photos |
| April 4, 2002
8:00 Am -11:30 Am |
Concrete Balcony slab |
Units # :TS-1, 2601, 2001, 1601, 1401, 1101,
1001, 701 |
Inspected balcony concrete areas for rusted
rebar, spalling removal and cleaning of surface for pour |
Contractor was instructed to clean rebars
from all rust, remove additional spalled concrete, cut rebars were cover is
required ..Reference Log Book for
details, took digital photos |
| April 8, 2002
9:00 Am - 11:00 Am |
Concrete Balcony Slab |
Units #: TS-01, 2601, 2001, 901 |
Inspected balcony concrete areas for rusted
rebar, spalling removal and cleaning of surface for pour |
Contractor was instructed to clean rebars
from all rust, remove additional spalled concrete, cut rebars were cover is
required ..Reference Log Book for details. |
| April 10, 2002
9:00 Am - 11:30 Am |
Concrete Balcony Slab |
Units #: 1701, 1301, 1101, 901, 701 |
Inspected balcony concrete areas for rusted
rebar, spalling removal and cleaning of surface for pour |
Contractor was instructed to clean rebars
from all rust, remove additional spalled concrete, cut rebars were cover is
required ..Reference Log Book for details. |
| April 16, 2002
9:30 Am - 11:30 Am |
Concrete Balcony Slab |
Units #: 610, 1001, 1101, 1601, 901, 2001,
1201, 1401, 1601, 2401, & PH-1. |
Inspected balcony concrete areas for cleaning of surface
and concrete hydro cement pour finish. |
Concrete finish is acceptable ..Reference Log
Book for details. |
| September 4, 2001 |
Initial site inspections and investigation of
spalled areas |
UNITS #:1901, 1701, 1601, 1406, 1405, 1401,
PH-1, 1006, 801, 705, 309 |
Inspected balcony concrete areas for rusted
rebar, spalling Concrete damage for engineering assessment and
specifications & recommendations |
Preliminary site inspections |
Photos Taken @ 9:00 to 11:30 AM, Friday March 29,
2002
      
Photos Taken @ 9:00 to 11:30 AM, Thursday April 4,
2002
      
 
Photos Taken @ 9:00 to 11:30 AM,
Wednesday April 10,
2002
      
      
Back
to Top

|